Tower Crane Dismantling Method Statement Jun 2026

The following steps outline the typical dismantling procedure for a tower crane:

The following safety measures will be implemented during the dismantling process:

| Condition | Action | |-----------|--------| | Wind speed > 20 mph (9 m/s) | Stop all lifts above 50ft height. | | Wind speed > 25 mph (11 m/s) | – secure partial load. | | Rain / fog (visibility < 50m) | Stop work. | | Lightning within 10 miles | Stop work, evacuate crane area. | | Night work | Only permitted with full lighting (500 lux minimum). | tower crane dismantling method statement

Disassemble the base chassis or unbolt the anchor mast section from the concrete foundation. Clean and secure all reusable foundation anchor hardware. 7. Safety Measures and Emergency Procedures Fall Prevention

Tag lines (minimum two) to control the swing of suspended components. Hydraulic pin pushers and impact wrenches. | | Lightning within 10 miles | Stop

Tower cranes are commonly used in construction sites to lift and move heavy loads. However, when a construction project is completed, the tower crane needs to be dismantled and removed from the site. Dismantling a tower crane is a complex process that requires careful planning, specialized equipment, and trained personnel. This method statement outlines the steps and procedures for safely dismantling a tower crane.

Riggers must remain tied off to certified anchor points 100% of the time while working on the mast, jib, or platforms. When transitioning between points, dual lanyards must be used to ensure continuous connection. Dropped Objects Prevention Clean and secure all reusable foundation anchor hardware

Dismantling operations must cease immediately if ambient wind speeds exceed , or the lower limit specified by the crane manufacturer.